Overview

  • Highway 1 Segment 2 construction is about 45-50% complete.
  • $7.7 million in additional costs identified; $1.5 million in savings found.
  • Contingency fund increased from 5% to 10% due to unforeseen issues.
  • Major cost drivers: design changes, unforeseen site conditions, tree removal, and public safety measures.
  • Commissioners raised concerns about cost overruns, transparency, and future funding impacts.

Highway 1 Project Status and Partnerships

  • RTC delivered Highway 1 corridor improvements, including Bus and Shoulder Auxiliary Lanes.
  • Segment 1  ... 