10/2/25 SCCRTC Part 5 - Coastal Trail Project Delivery
Santa Cruz County Transit and Transportation Agency Meetings... di Keith Bontrager
Note sull'episodio
Overview
- Coastal Rail Trail Segments 8-11 face significant funding and delivery challenges.
- Escalating costs and funding gaps threaten project timelines and scope.
- Multiple phasing and scope reduction options analyzed; none fully close the funding gap.
- $19.5M federal RAISE grant and $20.5M Safe Streets for All grant (pending) are key funding sources.
- Measure D sales tax is critical for leveraging state and federal funds, but is insufficient for full buildout.
- Project delivery is at risk due to strict grant deadlines and limited new funding opportunities.
Project Introduction and Recusal for Conflict of Interest
- Coastal Rail Trail Segments 8 ...