Overview
- Measure D active transportation projects are progressing faster than pay-as-you-go funding allows, necessitating new financing options.
- Over $150 million in state and federal funds have been leveraged for the coastal rail trail.
- Recent project completions include segment 7 to the Santa Cruz Wharf and new funding for segment 12.
- Cost estimates have increased due to material and escalation costs, creating a significant funding gap.
- Three financing scenarios were presented, with borrowing needs ranging from $12.5 million to $55 million.